Stage 1: 2007

Late 2006Initial proposals and ideas developed
February – March 2007 Consultation events
March 2007Proposals finalised
March 2007HLF Stage 1 submission
March – September 2007Proposals revisited and further information supplied to HLF
March 2008Heritage Lottery Fund (HLF) Stage 1 Bid approved for Stage 2 Development Funding

Stage 2: July 2008 - September 2009 - Project Delivery

July 2008Work commences on developing stage 1 Proposals
November 2008Illuminations Consultation Event
December and January 2008/09 Proposals refined and detailed
February  / March 2009Consultation Events
September 2009 HLF Stage 2 Submission – Stage 2 bid submitted
March / April 2010 HLF Decision announced (Anticipated date)
2010 Works start on site (Anticipated date)
Late 2011 / early 2012Visitor Centre opened (Anticipated date)
2013 Work completed (Anticipated date)